Ahmedabad: Construction of a 36-meter-high bridge over the Sabarmati River is progressing steadily as part of the Mumbai-Ahmedabad High-Speed Rail (Bullet Train) project, with several key structural milestones already achieved, officials said.
It is situated between the proposed Sabarmati and Ahmedabad high-speed rail stations, around one km from Sabarmati station and about four km from Ahmedabad station.
All eight circular piers, each measuring between 6 and 6.5 metres in diameter, have been completed. Four of these are located within the riverbed, two on the banks, and two outside the riverbanks.
The pier heights range between approximately 31 and 34 metres, and their placement has been designed to reduce interference with the river’s natural flow.
The bridge comprises five spans of 76 metres and two spans of 50 metres. Each span is being constructed using 23 segments cast in situ.
Officials said that foundation and substructure works have been completed, marking a significant stage in construction. Three of the 76-metre spans have been completed, while work on the remaining superstructure, including pier head construction and segment casting, is ongoing.
According to recent official updates, substantial progress has been made across the corridor, with hundreds of kilometres of viaduct and pier work completed and construction advancing simultaneously at stations, depots and bridge sites.